The Relationship between Building Agents in the Context of Integrated Project Management: A Prospective Analysis

Identificadores
URI: http://hdl.handle.net/10498/25292
DOI: 10.3390/buildings11050184
ISSN: 2075-5309
Files
Statistics
Metrics and citations
Metadata
Show full item recordDate
2021-05Department
Ingeniería Mecánica y Diseño IndustrialSource
Buildings 2021, 11(5), 184Abstract
The increasing complexity of building projects, with high quality standards, integrated
technologies and strong management restrictions, demands the intervention of numerous and diverse
specialists. This requires an intense leadership, organization and coordination effort. However,
building regulations, such as the Spanish Law on Building Management (LOE) 38/1999, only
formally consider developers, project designers, project and work supervisors, quality control entities,
construction companies, owners and final users as building agents. However, these categories are
insufficient to represent the interests of all the stakeholders. The purpose of this paper is to carry out
an analysis of the agents that are currently part of the entire building process. If their relationship of
influence and dependence, as well as their alignment with the overall objectives of the project are
studied, potential convergences, divergences, agreements and disagreements can be established. To
do this, the authors conducted a prospective analysis through the MACTOR (Matrix of Alliances
and Conflicts: Tactics, Objectives and Recommendations) strategic planning simulation tool, for
which the rules of the Delphi technique were applied and a consultation with technical experts,
both professionals and academics, was held. The research provides insight to assess the power
relationships between the building agents, as well as to measure the alignment of objectives with their
interests. Results show that, in the context of integrated project management (IPM), the influence of
technical agents is reduced by limiting their functions to those marked by their regulatory framework,
allowing them to focus on their legal powers, and the room for manoeuvre of the professional agents,
who are subject to systematized monitoring and control, is also reduced. The prospective analysis
also highlights the importance of defining the scope from its early stages, as well as the need to reach
multilateral agreements based on the other two main constraints: time and cost.
Subjects
building agents; building sector; prospective analysis; strategic planning; stakeholder analysis; integrated project managementCollections
- Artículos Científicos [11777]
- Articulos Científicos Ing. Mec. [320]






