RT journal article T1 Duration and cost variability of construction activities: an empirical study A1 Ballesteros Pérez, Pablo A1 Sanz Ablanedo, Enoc A1 Soetanto, Robby A1 González-Cruz, María Carmen A1 Larsen, Graeme D A1 Cerezo Narváez, Alberto A2 Ingeniería Mecánica y Diseño Industrial K1 scheduling K1 activity variability K1 merge event bias K1 network topology K1 project delays AB The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. As this variability is unplanned it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project, rather than their specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5000 activities. To do this, the first four moments (mean, standard deviation, skewness and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data. PB American Society of Civil Engineers SN 1943–7862 YR 2020 FD 2020-01-01 LK http://hdl.handle.net/10498/29947 UL http://hdl.handle.net/10498/29947 LA eng DS Repositorio Institucional de la Universidad de Cádiz RD 07-nov-2026