Comparison of the Stability and Accuracy of Deterministic Project Cost Prediction Methods in Earned Value Management

Thumbnail
Identificadores

URI: http://hdl.handle.net/10498/29944

DOI: 10.3390/buildings13051206

ISSN: 2352–4847

Files
Artículo (4.498Mb)
Statistics
View statistics
Metrics and citations
 
Share
Export
Export reference to MendeleyRefworksEndNoteBibTexRIS
Metadata
Show full item record
Author/s
Barrientos Orellana, Alexis; Ballesteros Pérez, PabloAuthority UCA; Mora Melià, Daniel; Cerezo Narváez, AlbertoAuthority UCA; Gutiérrez Bahamondes, Jimmy H.
Date
2023-05-02
Department
Ingeniería Mecánica y Diseño Industrial
Source
Buildings - 2023, Vol. 13, n.15 pp. 1206
Abstract
Completing a project on time and on budget are essential factors for the success of any project. One technique that allows predicting the final cost of a project is earned value management (EVM). In this technique, different mathematical methods for predicting the final project cost have been proposed over the last 30 years. These formulas make use of activities’ actual costs and durations as the project progresses. EVM is a technique widely used by many project management professionals. However, very few studies have compared the stability and accuracy of the multiple existing methods for predicting the final cost of the project (commonly abbreviated as estimated cost at completion, EAC). This study compares the stability and accuracy of 30 deterministic cost prediction methods (EAC) in EVM. For this purpose, a representative database of 4100 simulated projects of various topological structures is used. Our results suggest that the methods with the simplest mathematical configurations achieve better stability and accuracy performance. Knowing which EVM methods are the most stable and accurate for predicting the final cost of the project will help project practitioners choose the most reliable cost prediction techniques when they are managing their own projects in real contexts.
Subjects
accuracy; cost prediction methods; earned value analysis; stability; topological structure
Collections
  • Artículos Científicos [11620]
  • Articulos Científicos Ing. Mec. [314]
Attribution-NonCommercial-NoDerivatives 4.0 Internacional
This work is under a Creative Commons License Attribution-NonCommercial-NoDerivatives 4.0 Internacional

Browse

All of RODINCommunities and CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

My Account

LoginRegister

Statistics

View Usage Statistics

Información adicional

AboutDeposit in RODINPoliciesGuidelinesRightsLinksStatisticsNewsFrequently Asked Questions

RODIN is available through

OpenAIREOAIsterRecolectaHispanaEuropeanaBaseDARTOATDGoogle Academic

Related links

Sherpa/RomeoDulcineaROAROpenDOARCreative CommonsORCID

RODIN está gestionado por el Área de Biblioteca, Archivo y Publicaciones de la Universidad de Cádiz

Contact informationSuggestionsUser Support