Forecasting Accuracy of In-Progress Activity Duration and Cost Estimates

Thumbnail
Identificadores

URI: http://hdl.handle.net/10498/29946

DOI: 10.1061/(ASCE)CO.1943–7862.0001900

ISSN: 1943–7862

Ficheros
Artículo (1.389Mb)
Estadísticas
Ver estadísticas
Métricas y Citas
 
Compartir
Exportar a
Exportar a MendeleyRefworksEndNoteBibTexRIS
Metadatos
Mostrar el registro completo del ítem
Autor/es
Ballesteros Pérez, PabloAutoridad UCA; Sanz Ablanedo, Enoc; Cerezo Narváez, AlbertoAutoridad UCA; Lucko, Gunnar; Pastor Fernández, AndrésAutoridad UCA; Otero Mateo, ManuelAutoridad UCA; Contreras Samper, Juan PabloAutoridad UCA
Fecha
2020-09-01
Departamento/s
Ingeniería Mecánica y Diseño Industrial
Fuente
Journal of Construction Engineering and Management - 2020, Vol. 146, n. 9 pp. 04020104
Resumen
When a project activity has already started, tracking information such as percent complete and current activity duration and cost can be easily retrieved. This information can be used to update the project schedule to anticipate the eventual project duration and cost more precisely. But hardly any studies exist that compare how more accurate or reliable activity tracking information can be compared to the initial (planned) estimates, let alone what mathematical forecasting expressions are the most accurate. Therefore this paper quantifies said forecasting accuracy by extracting over three thousand activities with partial tracking information (which have already started, but are not yet complete) from a real project dataset. Two expressions for forecasting the activity duration and cost are tested by comparing their performance against initial (planned) and final (actual) values. The contributions to the body of knowledge are fourfold. First, it is shown that activity tracking information considerably outperforms planned estimates. Second, using two expressions can significantly minimize the deviations of time and cost estimates. Third, remaining activities’ duration and cost estimates can be closely modeled with Lognormal distributions as a function of the activities’ percent complete. And fourth, variability decreases linearly as activities approach their end. These findings allow project managers to better anticipate and model the duration and cost variability of ongoing activities and improve the forecasting accuracy of the project duration and cost estimates.
Materias
activity duration; activity cost; project; scheduling; tracking; forecasting
Colecciones
  • Artículos Científicos [12001]
  • Articulos Científicos Ing. Mec. [325]
Attribution-NonCommercial-NoDerivatives 4.0 Internacional
Esta obra está bajo una Licencia Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 Internacional

Listar

Todo RODINComunidades y ColeccionesPor fecha de publicaciónAutoresTítulosMateriasEsta colecciónPor fecha de publicaciónAutoresTítulosMaterias

Mi cuenta

AccederRegistro

Estadísticas

Ver Estadísticas de uso

Información adicional

Acerca de...Deposita en RODINPolíticasNormativasDerechos de autorEnlaces de interésEstadísticasNovedadesPreguntas frecuentes

RODIN está accesible a través de

OpenAIREOAIsterRecolectaHispanaEuropeanaBaseDARTOATDGoogle Académico

Enlaces de interés

Sherpa/RomeoDulcineaROAROpenDOARCreative CommonsORCID

RODIN está gestionado por el Área de Biblioteca, Archivo y Publicaciones de la Universidad de Cádiz

ContactoSugerenciasAtención al Usuario