dc.contributor.authorBallesteros Pérez, Pablo 
dc.contributor.authorSanz Ablanedo, Enoc
dc.contributor.authorSoetanto, Robby
dc.contributor.authorGonzález-Cruz, María Carmen
dc.contributor.authorLarsen, Graeme D
dc.contributor.authorCerezo Narváez, Alberto 
dc.contributor.otherIngeniería Mecánica y Diseño Industriales_ES
dc.date.accessioned2024-01-11T13:09:15Z
dc.date.available2024-01-11T13:09:15Z
dc.date.issued2020-01-01
dc.identifier.issn1943–7862
dc.identifier.urihttp://hdl.handle.net/10498/29947
dc.description.abstractThe unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. As this variability is unplanned it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project, rather than their specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5000 activities. To do this, the first four moments (mean, standard deviation, skewness and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data.es_ES
dc.formatapplication/pdfes_ES
dc.language.isoenges_ES
dc.publisherAmerican Society of Civil Engineerses_ES
dc.rightsAttribution-NonCommercial-NoDerivatives 4.0 Internacional*
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/4.0/*
dc.sourceJournal of Construction Engineering and Management - 2020, Vol. 146, n.1 pp. 04019093es_ES
dc.subjectschedulinges_ES
dc.subjectactivity variabilityes_ES
dc.subjectmerge event biases_ES
dc.subjectnetwork topologyes_ES
dc.subjectproject delayses_ES
dc.titleDuration and cost variability of construction activities: an empirical studyes_ES
dc.typejournal articlees_ES
dc.rights.accessRightsopen accesses_ES
dc.identifier.doi10.1061/(ASCE)CO.1943-7862.0001739
dc.relation.projectIDinfo:eu-repo/grantAgreement/MCIU//RYC-2017-22222//AYUDAS RAMON Y CAJAL/es_ES
dc.type.hasVersionAMes_ES


Ficheros en el ítem

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Attribution-NonCommercial-NoDerivatives 4.0 Internacional
Esta obra está bajo una Licencia Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 Internacional