Duration and cost variability of construction activities: an empirical study
| dc.contributor.author | Ballesteros Pérez, Pablo | |
| dc.contributor.author | Sanz Ablanedo, Enoc | |
| dc.contributor.author | Soetanto, Robby | |
| dc.contributor.author | González-Cruz, María Carmen | |
| dc.contributor.author | Larsen, Graeme D | |
| dc.contributor.author | Cerezo Narváez, Alberto | |
| dc.contributor.other | Ingeniería Mecánica y Diseño Industrial | es_ES |
| dc.date.accessioned | 2024-01-11T13:09:15Z | |
| dc.date.available | 2024-01-11T13:09:15Z | |
| dc.date.issued | 2020-01-01 | |
| dc.identifier.issn | 1943–7862 | |
| dc.identifier.uri | http://hdl.handle.net/10498/29947 | |
| dc.description.abstract | The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. As this variability is unplanned it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project, rather than their specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5000 activities. To do this, the first four moments (mean, standard deviation, skewness and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data. | es_ES |
| dc.format | application/pdf | es_ES |
| dc.language.iso | eng | es_ES |
| dc.publisher | American Society of Civil Engineers | es_ES |
| dc.rights | Attribution-NonCommercial-NoDerivatives 4.0 Internacional | * |
| dc.rights.uri | http://creativecommons.org/licenses/by-nc-nd/4.0/ | * |
| dc.source | Journal of Construction Engineering and Management - 2020, Vol. 146, n.1 pp. 04019093 | es_ES |
| dc.subject | scheduling | es_ES |
| dc.subject | activity variability | es_ES |
| dc.subject | merge event bias | es_ES |
| dc.subject | network topology | es_ES |
| dc.subject | project delays | es_ES |
| dc.title | Duration and cost variability of construction activities: an empirical study | es_ES |
| dc.type | journal article | es_ES |
| dc.rights.accessRights | open access | es_ES |
| dc.identifier.doi | 10.1061/(ASCE)CO.1943-7862.0001739 | |
| dc.relation.projectID | info:eu-repo/grantAgreement/MCIU//RYC-2017-22222//AYUDAS RAMON Y CAJAL/ | es_ES |
| dc.type.hasVersion | AM | es_ES |
Ficheros en el ítem
Este ítem aparece en la(s) siguiente(s) colección(ones)
-
Artículos Científicos [12014]
-
Articulos Científicos Ing. Mec. [325]