Duration and cost variability of construction activities: an empirical study

Thumbnail
Identificadores

URI: http://hdl.handle.net/10498/29947

DOI: 10.1061/(ASCE)CO.1943-7862.0001739

ISSN: 1943–7862

Files
Artículo (938.6Kb)
Statistics
View statistics
Metrics and citations
 
Share
Export
Export reference to MendeleyRefworksEndNoteBibTexRIS
Metadata
Show full item record
Author/s
Ballesteros Pérez, PabloAuthority UCA; Sanz Ablanedo, Enoc; Soetanto, Robby; González-Cruz, María Carmen; Larsen, Graeme D; Cerezo Narváez, AlbertoAuthority UCA
Date
2020-01-01
Department
Ingeniería Mecánica y Diseño Industrial
Source
Journal of Construction Engineering and Management - 2020, Vol. 146, n.1 pp. 04019093
Abstract
The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. As this variability is unplanned it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project, rather than their specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5000 activities. To do this, the first four moments (mean, standard deviation, skewness and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data.
Subjects
scheduling; activity variability; merge event bias; network topology; project delays
Collections
  • Artículos Científicos [11968]
  • Articulos Científicos Ing. Mec. [325]
Attribution-NonCommercial-NoDerivatives 4.0 Internacional
This work is under a Creative Commons License Attribution-NonCommercial-NoDerivatives 4.0 Internacional

Browse

All of RODINCommunities and CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

My Account

LoginRegister

Statistics

View Usage Statistics

Información adicional

AboutDeposit in RODINPoliciesGuidelinesRightsLinksStatisticsNewsFrequently Asked Questions

RODIN is available through

OpenAIREOAIsterRecolectaHispanaEuropeanaBaseDARTOATDGoogle Academic

Related links

Sherpa/RomeoDulcineaROAROpenDOARCreative CommonsORCID

RODIN está gestionado por el Área de Biblioteca, Archivo y Publicaciones de la Universidad de Cádiz

Contact informationSuggestionsUser Support