Comparison of the Stability and Accuracy of Deterministic Project Cost Prediction Methods in Earned Value Management

Thumbnail
Identificadores

URI: http://hdl.handle.net/10498/29944

DOI: 10.3390/buildings13051206

ISSN: 2352–4847

Ficheros
Artículo (4.498Mb)
Estadísticas
Ver estadísticas
Métricas y Citas
 
Compartir
Exportar a
Exportar a MendeleyRefworksEndNoteBibTexRIS
Metadatos
Mostrar el registro completo del ítem
Autor/es
Barrientos Orellana, Alexis; Ballesteros Pérez, PabloAutoridad UCA; Mora Melià, Daniel; Cerezo Narváez, AlbertoAutoridad UCA; Gutiérrez Bahamondes, Jimmy H.
Fecha
2023-05-02
Departamento/s
Ingeniería Mecánica y Diseño Industrial
Fuente
Buildings - 2023, Vol. 13, n.15 pp. 1206
Resumen
Completing a project on time and on budget are essential factors for the success of any project. One technique that allows predicting the final cost of a project is earned value management (EVM). In this technique, different mathematical methods for predicting the final project cost have been proposed over the last 30 years. These formulas make use of activities’ actual costs and durations as the project progresses. EVM is a technique widely used by many project management professionals. However, very few studies have compared the stability and accuracy of the multiple existing methods for predicting the final cost of the project (commonly abbreviated as estimated cost at completion, EAC). This study compares the stability and accuracy of 30 deterministic cost prediction methods (EAC) in EVM. For this purpose, a representative database of 4100 simulated projects of various topological structures is used. Our results suggest that the methods with the simplest mathematical configurations achieve better stability and accuracy performance. Knowing which EVM methods are the most stable and accurate for predicting the final cost of the project will help project practitioners choose the most reliable cost prediction techniques when they are managing their own projects in real contexts.
Materias
accuracy; cost prediction methods; earned value analysis; stability; topological structure
Colecciones
  • Artículos Científicos [12006]
  • Articulos Científicos Ing. Mec. [325]
Attribution-NonCommercial-NoDerivatives 4.0 Internacional
Esta obra está bajo una Licencia Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 Internacional

Listar

Todo RODINComunidades y ColeccionesPor fecha de publicaciónAutoresTítulosMateriasEsta colecciónPor fecha de publicaciónAutoresTítulosMaterias

Mi cuenta

AccederRegistro

Estadísticas

Ver Estadísticas de uso

Información adicional

Acerca de...Deposita en RODINPolíticasNormativasDerechos de autorEnlaces de interésEstadísticasNovedadesPreguntas frecuentes

RODIN está accesible a través de

OpenAIREOAIsterRecolectaHispanaEuropeanaBaseDARTOATDGoogle Académico

Enlaces de interés

Sherpa/RomeoDulcineaROAROpenDOARCreative CommonsORCID

RODIN está gestionado por el Área de Biblioteca, Archivo y Publicaciones de la Universidad de Cádiz

ContactoSugerenciasAtención al Usuario