Forecasting the Project Duration Average and Standard Deviation from Deterministic Schedule Information

Thumbnail
Identificadores

URI: http://hdl.handle.net/10498/22971

DOI: 10.3390/app10020654

ISSN: 2076-3417

Files
SC2020_010.pdf (1.388Mb)
Statistics
View statistics
Metrics and citations
 
Share
Export
Export reference to MendeleyRefworksEndNoteBibTexRIS
Metadata
Show full item record
Author/s
Ballesteros Pérez, PabloAuthority UCA; Cerezo Narváez, AlbertoAuthority UCA; Otero Mateo, ManuelAuthority UCA; Pastor Fernández, AndrésAuthority UCA; Zhang, Jingxiao; Vanhoucke, Mario
Date
2020-01
Department
Ingeniería Mecánica y Diseño Industrial
Source
Appl. Sci. 2020, 10(2), 654
Abstract
Most construction managers use deterministic scheduling techniques to plan construction projects and estimate their duration. However, deterministic techniques are known to underestimate the project duration. Alternative methods, such as Stochastic Network Analysis, have rarely been adopted in practical contexts as they are commonly computer-intensive, require extensive historical information, have limited contextual/local validity and/or require skills most practitioners have not been trained for. In this paper, we propose some mathematical expressions to approximate the average and the standard deviation of a project duration from basic deterministic schedule information. The expressions’ performance is successfully tested in a 4100-network dataset with varied activity durations and activity durations variability. Calculations are quite straightforward and can be implemented manually. Furthermore, unlike the Project Evaluation and Review Technique (PERT), they allow drawing inferences about the probability of project duration in the presence of several critical and subcritical paths with minimal additional calculation.
Subjects
project duration; scheduling; merge event bias; construction; PERT
Collections
  • Artículos Científicos [11954]
  • Articulos Científicos Ing. Mec. [324]
Atribución 4.0 Internacional
This work is under a Creative Commons License Atribución 4.0 Internacional

Browse

All of RODINCommunities and CollectionsBy Issue DateAuthorsTitlesSubjectsThis CollectionBy Issue DateAuthorsTitlesSubjects

My Account

LoginRegister

Statistics

View Usage Statistics

Información adicional

AboutDeposit in RODINPoliciesGuidelinesRightsLinksStatisticsNewsFrequently Asked Questions

RODIN is available through

OpenAIREOAIsterRecolectaHispanaEuropeanaBaseDARTOATDGoogle Academic

Related links

Sherpa/RomeoDulcineaROAROpenDOARCreative CommonsORCID

RODIN está gestionado por el Área de Biblioteca, Archivo y Publicaciones de la Universidad de Cádiz

Contact informationSuggestionsUser Support