Forecasting the Project Duration Average and Standard Deviation from Deterministic Schedule Information

Files
Statistics
Metrics and citations
Metadata
Show full item recordDate
2020-01Department
Ingeniería Mecánica y Diseño IndustrialSource
Appl. Sci. 2020, 10(2), 654Abstract
Most construction managers use deterministic scheduling techniques to plan construction
projects and estimate their duration. However, deterministic techniques are known to underestimate
the project duration. Alternative methods, such as Stochastic Network Analysis, have rarely been
adopted in practical contexts as they are commonly computer-intensive, require extensive historical
information, have limited contextual/local validity and/or require skills most practitioners have
not been trained for. In this paper, we propose some mathematical expressions to approximate
the average and the standard deviation of a project duration from basic deterministic schedule
information. The expressions’ performance is successfully tested in a 4100-network dataset with
varied activity durations and activity durations variability. Calculations are quite straightforward and
can be implemented manually. Furthermore, unlike the Project Evaluation and Review Technique
(PERT), they allow drawing inferences about the probability of project duration in the presence of
several critical and subcritical paths with minimal additional calculation.
Subjects
project duration; scheduling; merge event bias; construction; PERTCollections