Forecasting the Project Duration Average and Standard Deviation from Deterministic Schedule Information

Thumbnail
Identificadores

URI: http://hdl.handle.net/10498/22971

DOI: 10.3390/app10020654

ISSN: 2076-3417

Ficheros
SC2020_010.pdf (1.388Mb)
Estadísticas
Ver estadísticas
Métricas y Citas
 
Compartir
Exportar a
Exportar a MendeleyRefworksEndNoteBibTexRIS
Metadatos
Mostrar el registro completo del ítem
Autor/es
Ballesteros Pérez, PabloAutoridad UCA; Cerezo Narváez, AlbertoAutoridad UCA; Otero Mateo, ManuelAutoridad UCA; Pastor Fernández, AndrésAutoridad UCA; Zhang, Jingxiao; Vanhoucke, Mario
Fecha
2020-01
Departamento/s
Ingeniería Mecánica y Diseño Industrial
Fuente
Appl. Sci. 2020, 10(2), 654
Resumen
Most construction managers use deterministic scheduling techniques to plan construction projects and estimate their duration. However, deterministic techniques are known to underestimate the project duration. Alternative methods, such as Stochastic Network Analysis, have rarely been adopted in practical contexts as they are commonly computer-intensive, require extensive historical information, have limited contextual/local validity and/or require skills most practitioners have not been trained for. In this paper, we propose some mathematical expressions to approximate the average and the standard deviation of a project duration from basic deterministic schedule information. The expressions’ performance is successfully tested in a 4100-network dataset with varied activity durations and activity durations variability. Calculations are quite straightforward and can be implemented manually. Furthermore, unlike the Project Evaluation and Review Technique (PERT), they allow drawing inferences about the probability of project duration in the presence of several critical and subcritical paths with minimal additional calculation.
Materias
project duration; scheduling; merge event bias; construction; PERT
Colecciones
  • Artículos Científicos [11977]
  • Articulos Científicos Ing. Mec. [325]
Atribución 4.0 Internacional
Esta obra está bajo una Licencia Creative Commons Atribución 4.0 Internacional

Listar

Todo RODINComunidades y ColeccionesPor fecha de publicaciónAutoresTítulosMateriasEsta colecciónPor fecha de publicaciónAutoresTítulosMaterias

Mi cuenta

AccederRegistro

Estadísticas

Ver Estadísticas de uso

Información adicional

Acerca de...Deposita en RODINPolíticasNormativasDerechos de autorEnlaces de interésEstadísticasNovedadesPreguntas frecuentes

RODIN está accesible a través de

OpenAIREOAIsterRecolectaHispanaEuropeanaBaseDARTOATDGoogle Académico

Enlaces de interés

Sherpa/RomeoDulcineaROAROpenDOARCreative CommonsORCID

RODIN está gestionado por el Área de Biblioteca, Archivo y Publicaciones de la Universidad de Cádiz

ContactoSugerenciasAtención al Usuario